West Berkshire Brewery Installation Services

WBB.png

West Berkshire Brewery has purchased a brewery and packaging lines from CFT. 

Ambro was contracted on extremely short notice (3 working days) to provide a full site installation team comprising of lift and shift, 6 mechanical installers, 6 welders / fitters and 4 electrical installers.

The contacts and experience of the team at Ambro enabled us to pull together a team of subcontractors for the client. Ambro engineers were in daily contact with the site team and attended site regularly to ensure that the project manager and principal contractor were both satisfied with the work. In all, installation services were provided to West Berkshire Brewery for 3 months.

Edward Scott